Decommissioning of Galway Bay Wave Energy Test Site.
Wednesday, 13 September 2017
Marine Notice No. 38 of 2017
Amended on 12/09/2017
Notice to all Shipowners, Fishing Vessel Owners, Agents, Shipmasters, Skippers, Fishers and Seafarers
The Department of Transport, Tourism and Sport have been advised that the Marine Institute are decommissioning the wave energy test site in Galway Bay. The decommissioning will involve the removal of four cardinal marks and the establishment of a new special mark.
The “Chateau Thierry” (Callsign EIHK6) is scheduled to arrive on site between the 11th and 18th September 2017 to install the new Special Mark and remove the four Cardinal Marks. The duration of the operation will be approximately 2 days depending upon weather or other operational conditions. It is anticipated that the decommissioning operation will be completed on or before the 19th September 2017.
The location of the Galway Bay test site is shown in Figure 1 below:
Figure 1: Location of Galway Bay test site.
Decommissioning of Galway Bay Wave Energy Test Site.
Marine Notice No. 38 of 2017
Amended on 12/09/2017
Notice to all Shipowners, Fishing Vessel Owners, Agents, Shipmasters, Skippers, Fishers and Seafarers
The Department of Transport, Tourism and Sport have been advised that the Marine Institute are decommissioning the wave energy test site in Galway Bay. The decommissioning will involve the removal of four cardinal marks and the establishment of a new special mark.
The “Chateau Thierry” (Callsign EIHK6) is scheduled to arrive on site between the 11th and 18th September 2017 to install the new Special Mark and remove the four Cardinal Marks. The duration of the operation will be approximately 2 days depending upon weather or other operational conditions. It is anticipated that the decommissioning operation will be completed on or before the 19th September 2017.
The location of the Galway Bay test site is shown in Figure 1 below:
Figure 1: Location of Galway Bay test site.
Cardinal Marks to be removed
The decommission operation will involve the removal of a wave monitoring data buoy from the site and the removal of the four existing Cardinal Marks located at the following coordinates: Latitude |
|
53o 13.906’ N | 009o 16.148’ W |
53o 13.598’ N | 009o 16.151’ W |
53o 13.906’ N | 00 9o 15.540’ W |
53o 13.598’ N | 009o 15.543’ W |
Cardinal Marks to be removed
The decommission operation will involve the removal of a wave monitoring data buoy from the site and the removal of the four existing Cardinal Marks located at the following coordinates: Latitude |
|
53o 13.906’ N | 009o 16.148’ W |
53o 13.598’ N | 009o 16.151’ W |
53o 13.906’ N | 00 9o 15.540’ W |
presented by Cathy McLeanhttp://www.bymnews BYM where the news is read. 1.5 Million News items opened Jan. 1- Apr. 30 2017 Our readership http://www.bymnews.com/pdf/january-june-2017-statistics.pdf Two for the price of one a place on one of our 3 carousels plus a PDF in BYM magazine, embedded images included Just $42.50 PCM Detailshttp://www.bymnews.com/demo/display-carousel.html 53o 13.598’ N | 009o 15.543’ W
|